March 2025 - Overview of expansion lane
March 2025 - Overview of expansion lane
March 2025 - Overview of expansion lane
Girder Installation - January 15-17, 2025:
Wed. Jan 15/25 ( 12:30 pm) - 1st Girder installed on South (left) side
Fri. Jan.17/25 (9:50 am)- 1st Girder installed on North (right) side

Fri. jan. 17/25 (12:45 pm)- Final Girder installed on North (right) side
|
Location:
|
London
|
Owner:
|
City of London
|
Contract Type:
|
Subcontract to Bre-Ex Limited
|
Engineer:
|
Dillon Consulting
|
Value:
|
$6,500,000
|
Started:
|
May 2024
|
Completed:
|
June 2025
|
Description:
|
This 2-lane expansion to the existing 4-lane vehicular bridge over the Thames River will allow for the new BRT (Bus Rapid Transit) system.
The completed project will have 2 lanes in each direction for regular traffic, with the 2 centre lanes reserved for the BRT.
|
|