Stair / Elevator Tower and Concrete Slabs on Deck (Plus 4-Level Underground Parking Garage)
Our concrete structure work
Finished project (by others)
Location:
London
Owner:
Sifton Properties Limited, London
London Life Insurance Company
Contract Type:
Subcontract to PCL Construction
Architect:
Crang and Boake Inc., Don Mills
Value:
$7,624,000
No. of Storeys:
22 (above ground)
5 (below ground)
Area:
Tower (above ground)
Footprint 17,650 sf / 1,640 sm
Gross Floor 388,000 sf / 36,060 sm
Parking Garage (underground)
Footprint 71,050 sf / 6,600 sm
Gross Floor 355,200 sf / 33,000 sm
Started:
March 1991
Completed:
April 1992
Description:
Our forces built 22 floors of concrete stair/elevator tower and floor slabs on steel deck, plus 4 floors of a reinforced concrete underground parking structure.